WEEK OF JANUARY 12, 2017

The Fiber Optic project has continued to show progress, with both aerial and underground construction. We have lit up the northern part of our service area with high speed internet services. Several businesses and residences in Questa, Costilla, Amalia, Taos, Taos Pueblo, Taos Ski Valley and Sipapu Ski & Summer Resort are connected to high speed internet. We are moving forward into 2017 to have our entire service area connected at light speed. Approximately 85% of the project is complete.

Testing began January 12, 2017 in Eagle Nest, Red River, Angel Fire and Taos. If testing is successful these areas will be lit and ready for service by January 31, 2017.

Main Line Construction Project is approximately 92% complete.

*We have crews doing fiber drops in all areas North of Questa & Taos Pueblo.

*The Fiber Drop underground installations may cease in any areas that the ground frost depth reaches 6 inches, these areas will resume in the spring thaw.

*The Aerial Fiber Drops will continue thru the winter months, with weather permitting.

If you would like to know more about the Fiber Drops

click here for a detailed explanation.

WE ARE MOVING FORWARD AND WILL BE IN YOUR NEIGHBORHOOD SOON!!!